In shortசுருக்கமாக

When you buy an under-construction apartment, the builder usually splits the deal into two documents: a sale agreement for the undivided share of land, and a separate construction agreement for the building. That structure is normal and lawful. The trap is in how the two are drafted — a registered land document paired with an unregistered construction contract, payment schedules tied to time rather than progress, and a possession date that appears nowhere enforceable. This explainer shows what each document must contain and the clauses that decide who carries the risk.

கட்டுமானத்தில் உள்ள அடுக்குமாடி குடியிருப்பை வாங்கும்போது, பில்டர் பொதுவாக ஒப்பந்தத்தை இரண்டு ஆவணங்களாகப் பிரிக்கிறார்: நிலத்தின் பிரிக்கப்படாத பங்குக்கு (UDS) விற்பனை ஒப்பந்தம், கட்டிடத்திற்குத் தனியான கட்டுமான ஒப்பந்தம். இந்த அமைப்பு இயல்பானது, சட்டப்பூர்வமானது. வலை இருப்பது அவை எப்படி எழுதப்படுகின்றன என்பதில்தான் — பதிவு செய்யப்பட்ட நில ஆவணத்துடன் பதிவு செய்யப்படாத கட்டுமான ஒப்பந்தம், முன்னேற்றத்தை அல்ல காலத்தைச் சார்ந்த தவணை அட்டவணை, எங்கும் அமல்படுத்த முடியாத ஒப்படைப்புத் தேதி. ஒவ்வொரு ஆவணத்திலும் என்ன இருக்க வேண்டும், அபாயத்தை யார் சுமப்பது என்பதை எந்த விதிகள் தீர்மானிக்கின்றன — இவை இங்கே.

Key pointsமுக்கியக் குறிப்புகள்

  1. The sale agreement covers the undivided share of land; the construction agreement covers building your flat. You need both to be sound — a clean UDS with a weak construction contract still leaves you exposed.
  2. Register both agreements. An unregistered construction agreement is much harder to enforce and gives you little leverage when the schedule slips.
  3. Tie payments to construction milestones that can be physically verified, never to calendar dates alone.
  4. A project that must be registered under RERA and is not is a red flag by itself — check the regulator's website before you pay anything.
  5. Read the delay clause, the termination clause and the specification schedule. Those three decide what happens when things go wrong.
  1. விற்பனை ஒப்பந்தம் நிலத்தின் பிரிக்கப்படாத பங்கை உள்ளடக்குகிறது; கட்டுமான ஒப்பந்தம் உங்கள் வீட்டைக் கட்டுவதை. இரண்டும் உறுதியாக இருக்க வேண்டும் — தெளிவான UDS இருந்தும் பலவீனமான கட்டுமான ஒப்பந்தம் இருந்தால் நீங்கள் ஆபத்திலேயே.
  2. இரு ஒப்பந்தங்களையும் பதிவு செய்யுங்கள். பதிவு செய்யப்படாத கட்டுமான ஒப்பந்தத்தை அமல்படுத்துவது மிகக் கடினம்; அட்டவணை பிசகும்போது உங்களுக்கு எந்த வலிமையும் இருக்காது.
  3. தவணைகளை, நேரில் சரிபார்க்கக்கூடிய கட்டுமான மைல்கற்களுடன் இணையுங்கள்; வெறும் நாட்காட்டித் தேதிகளுடன் ஒருபோதும் அல்ல.
  4. RERA-வில் பதிவு செய்யப்பட வேண்டிய திட்டம் பதிவு செய்யப்படாமல் இருப்பதே ஓர் எச்சரிக்கை — எந்தப் பணமும் கட்டும் முன் ஒழுங்குமுறை அமைப்பின் இணையதளத்தில் சரிபாருங்கள்.
  5. தாமத விதி, ரத்து விதி, விவரக்குறிப்பு அட்டவணை — இந்த மூன்றையும் படியுங்கள். தவறு நடக்கும்போது என்ன ஆகும் என்பதை இவையே தீர்மானிக்கின்றன.

01Why builders split the deal in twoபில்டர்கள் ஏன் ஒப்பந்தத்தை இரண்டாகப் பிரிக்கிறார்கள்

In an apartment purchase you are buying two different things. The land under the building cannot be divided physically, so you get an undivided share in it, proportionate to your flat. That is immovable property and moves by a registered sale document. The flat itself does not exist yet; it is something the builder agrees to construct for you, which is a works contract.

Splitting the transaction reflects that reality, and it also changes the tax and stamp duty position, since duty on the land component and the taxation of the construction component are computed differently. That is legitimate, and every large developer does it.

The problem arises when the split is used to move risk onto you. The builder registers the land agreement — securing their money and your obligation — while keeping the construction agreement unregistered, vaguely specified, and silent on what happens if the building is late, changed or never finished.

அடுக்குமாடி வாங்கும்போது நீங்கள் இரண்டு வெவ்வேறு பொருட்களை வாங்குகிறீர்கள். கட்டிடத்தின் கீழுள்ள நிலத்தை உடல்ரீதியாகப் பிரிக்க முடியாது; எனவே உங்கள் வீட்டின் விகிதத்திற்கேற்ப அதில் பிரிக்கப்படாத பங்கு கிடைக்கிறது. அது அசையா சொத்து; பதிவு செய்யப்பட்ட விற்பனை ஆவணத்தால் மாறுகிறது. வீடு இன்னும் இல்லை; அதை உங்களுக்காகக் கட்டித் தருவதாக பில்டர் ஒப்புக்கொள்கிறார் — அது ஒரு பணி ஒப்பந்தம்.

பரிவர்த்தனையைப் பிரிப்பது இந்த யதார்த்தத்தைப் பிரதிபலிக்கிறது; வரி மற்றும் முத்திரைத் தீர்வை நிலையையும் மாற்றுகிறது — நிலப் பகுதிக்கான தீர்வையும், கட்டுமானப் பகுதிக்கான வரியும் வெவ்வேறு முறையில் கணக்கிடப்படுகின்றன. இது முறையானது; ஒவ்வொரு பெரிய டெவலப்பரும் இதைச் செய்கிறார்.

பிரிவினை அபாயத்தை உங்கள் மீது தள்ளப் பயன்படுத்தப்படும்போதே பிரச்சினை. பில்டர் நில ஒப்பந்தத்தைப் பதிவு செய்கிறார் — தன் பணத்தையும் உங்கள் கடமையையும் உறுதி செய்கிறார் — ஆனால் கட்டுமான ஒப்பந்தத்தை பதிவு செய்யாமல், தெளிவற்ற விவரக்குறிப்புகளுடன், கட்டிடம் தாமதமானால், மாற்றப்பட்டால், அல்லது முடிக்கப்படாவிட்டால் என்ன என்பதைப் பற்றி மௌனமாக வைத்திருக்கிறார்.

02What the sale agreement must get rightவிற்பனை ஒப்பந்தத்தில் சரியாக இருக்க வேண்டியவை

The undivided share must be stated as a specific extent — so many square feet out of the total, with the total extent and the total number of flats disclosed so you can check the arithmetic. A UDS quoted only as a percentage, without the underlying numbers, is not verifiable.

The land description must carry the survey numbers, boundaries and the approval reference for the project. The agreement should recite that the land is free from encumbrance and attach the title documents, and it should name the approving authority and the permit number for the building.

Check that the seller of the UDS is the person who actually owns the land. In joint development projects the landowner and the builder are different parties, and the builder sells your UDS under a development agreement and power of attorney. Read that development agreement — it defines what the builder is entitled to sell.

பிரிக்கப்படாத பங்கு ஒரு குறிப்பிட்ட அளவாகக் குறிப்பிடப்பட வேண்டும் — மொத்தத்தில் இத்தனை சதுர அடி; மொத்தப் பரப்பும் மொத்த வீடுகளின் எண்ணிக்கையும் வெளிப்படுத்தப்பட வேண்டும், நீங்கள் கணக்கைச் சரிபார்க்க. அடிப்படை எண்கள் இல்லாமல் சதவீதமாக மட்டும் சொல்லப்படும் UDS-ஐ சரிபார்க்க முடியாது.

நில விவரத்தில் புல எண்கள், எல்லைகள், திட்டத்திற்கான அனுமதிக் குறிப்பு இருக்க வேண்டும். நிலம் வில்லங்கமற்றது என்று ஒப்பந்தம் குறிப்பிட வேண்டும், உரிமை ஆவணங்களை இணைக்க வேண்டும்; கட்டிடத்திற்கான அனுமதி வழங்கிய அமைப்பையும் அனுமதி எண்ணையும் குறிப்பிட வேண்டும்.

UDS-ஐ விற்பவர், உண்மையில் நிலத்திற்கு உரிமையாளரா என்பதைச் சரிபாருங்கள். கூட்டு வளர்ச்சித் திட்டங்களில் நில உரிமையாளரும் பில்டரும் வெவ்வேறு தரப்பினர்; வளர்ச்சி ஒப்பந்தம் மற்றும் அதிகாரப் பத்திரத்தின் கீழ் பில்டர் உங்கள் UDS-ஐ விற்கிறார். அந்த வளர்ச்சி ஒப்பந்தத்தைப் படியுங்கள் — பில்டர் எதை விற்க உரிமை பெற்றுள்ளார் என்பதை அதுவே வரையறுக்கிறது.

03What the construction agreement must get rightகட்டுமான ஒப்பந்தத்தில் சரியாக இருக்க வேண்டியவை

Specifications must be an annexure, not adjectives. 'Premium vitrified tiles' means nothing; a brand, size, grade and where it is used means something. The same goes for cement grade, steel, wiring, sanitary ware, lift make and generator backup. Anything left as 'or equivalent' will be substituted downward.

The payment schedule must follow verifiable milestones — foundation complete, each floor slab cast, brickwork, plastering, flooring, handover. Time-linked instalments transfer the entire risk of delay to you, because you keep paying while nothing rises.

The carpet area, built-up area and super built-up area should each be stated separately, with the loading disclosed. You are paying per square foot of something; the agreement should make plain which something.

Finally, the delay clause. It should provide compensation payable to you at a stated rate per month of delay beyond the promised date, mirroring the penalty you pay for late instalments. A one-sided penalty clause tells you exactly how the relationship will run.

விவரக்குறிப்புகள் அடைமொழிகளாக அல்ல, இணைப்பாக இருக்க வேண்டும். 'ப்ரீமியம் விட்ரிஃபைடு டைல்ஸ்' என்பது எதையும் குறிக்காது; பிராண்ட், அளவு, தரம், எங்கு பயன்படுத்தப்படுகிறது என்பது ஏதோ ஒன்றைக் குறிக்கிறது. சிமெண்ட் தரம், இரும்பு, வயரிங், சானிட்டரி பொருட்கள், லிஃப்ட் நிறுவனம், ஜெனரேட்டர் ஆகியவற்றுக்கும் இதுவே. 'அல்லது அதற்கு இணையானது' என விடப்படும் எதுவும் தரம் குறைந்ததாக மாற்றப்படும்.

தவணை அட்டவணை சரிபார்க்கக்கூடிய மைல்கற்களைப் பின்பற்ற வேண்டும் — அடித்தளம் முடிவு, ஒவ்வொரு தள ஸ்லாப், செங்கல் வேலை, பூச்சு, தரை, ஒப்படைப்பு. காலத்தை அடிப்படையாகக் கொண்ட தவணைகள், தாமதத்தின் முழு அபாயத்தையும் உங்கள் மீது மாற்றுகின்றன — எதுவும் எழாமலேயே நீங்கள் பணம் கட்டிக்கொண்டிருப்பீர்கள்.

கார்பெட் ஏரியா, பில்ட்-அப் ஏரியா, சூப்பர் பில்ட்-அப் ஏரியா ஆகியவை தனித்தனியாகக் குறிப்பிடப்பட வேண்டும்; லோடிங் வெளிப்படுத்தப்பட வேண்டும். நீங்கள் ஏதோ ஒன்றின் சதுர அடிக்குப் பணம் கட்டுகிறீர்கள்; அது எது என்பதை ஒப்பந்தம் தெளிவாகச் சொல்ல வேண்டும்.

இறுதியாக, தாமத விதி. வாக்குறுதியளித்த தேதிக்குப் பிறகு ஒவ்வொரு மாதத் தாமதத்திற்கும் உங்களுக்குச் செலுத்த வேண்டிய இழப்பீட்டை, குறிப்பிட்ட விகிதத்தில் அது வழங்க வேண்டும் — தாமதமான தவணைக்கு நீங்கள் செலுத்தும் அபராதத்தைப் போலவே. ஒருதலைப்பட்ச அபராத விதி, இந்த உறவு எப்படி நடக்கும் என்பதைத் துல்லியமாகச் சொல்லிவிடும்.

04Where RERA changes the pictureRERA படத்தை எங்கு மாற்றுகிறது

Projects above the prescribed size threshold must be registered with the state real estate regulator before they can be advertised or sold. Registration brings obligations that work in your favour: disclosure of approvals and the project timeline, a separate account into which a defined share of buyer money must go and be used only for that project, and a defined process for complaints.

Check the regulator's portal for the project registration number, the approved plans, the promised completion date and any complaints filed. This is public information and takes minutes. A builder who cannot give you a registration number for a project that requires one has already told you something important.

RERA also gives you a forum. Disputes about delay, deviation from the sanctioned plan, or refusal to hand over can be taken to the authority rather than starting in a civil court, and orders can include interest and compensation. It is not a guarantee of a good outcome, but it changes the balance of leverage considerably from what it was a decade ago.

நிர்ணயிக்கப்பட்ட அளவுக்கு மேலான திட்டங்கள், விளம்பரப்படுத்தவோ விற்கவோ முன், மாநில ரியல் எஸ்டேட் ஒழுங்குமுறை ஆணையத்தில் பதிவு செய்யப்பட வேண்டும். இந்தப் பதிவு உங்களுக்குச் சாதகமான கடமைகளைக் கொண்டுவருகிறது: அனுமதிகள் மற்றும் திட்ட காலவரிசை வெளிப்படுத்தல்; வாங்குபவரின் பணத்தில் குறிப்பிட்ட பங்கு செல்ல வேண்டிய, அந்தத் திட்டத்திற்கு மட்டுமே பயன்படுத்தப்பட வேண்டிய தனிக் கணக்கு; புகார்களுக்கான வரையறுக்கப்பட்ட நடைமுறை.

ஒழுங்குமுறை அமைப்பின் இணையதளத்தில் திட்டப் பதிவு எண், அங்கீகரிக்கப்பட்ட வரைபடங்கள், வாக்குறுதியளிக்கப்பட்ட முடிவுத் தேதி, தாக்கல் செய்யப்பட்ட புகார்கள் ஆகியவற்றைச் சரிபாருங்கள். இது பொதுத் தகவல்; சில நிமிடங்களே ஆகும். பதிவு தேவைப்படும் திட்டத்திற்கு பதிவு எண் தர முடியாத பில்டர், ஏற்கனவே முக்கியமான ஒன்றைச் சொல்லிவிட்டார்.

RERA உங்களுக்கு ஒரு மன்றத்தையும் தருகிறது. தாமதம், அங்கீகரிக்கப்பட்ட வரைபடத்திலிருந்து விலகல், ஒப்படைக்க மறுப்பு தொடர்பான தகராறுகளை, சிவில் நீதிமன்றத்தில் தொடங்காமல் ஆணையத்திடம் எடுத்துச் செல்லலாம்; உத்தரவுகளில் வட்டியும் இழப்பீடும் அடங்கலாம். இது நல்ல முடிவுக்கு உத்தரவாதம் அல்ல; ஆனால் பத்தாண்டுகளுக்கு முன் இருந்ததை விட வலிமைச் சமநிலையை கணிசமாக மாற்றுகிறது.

What to do nextஅடுத்து என்ன செய்ய வேண்டும்

  1. Verify the project registration on the state RERA portal and download the approved plan and declared timeline.
  2. Ask for the UDS extent in square feet, the total land extent and the total number of flats — then check the arithmetic yourself.
  3. In a joint development, read the development agreement and power of attorney that authorise the builder to sell your UDS.
  4. Insist that specifications go in as a signed annexure with brands, grades and sizes — not adjectives.
  5. Rewrite the payment schedule to follow construction milestones, and require the delay compensation clause to mirror the late-payment penalty.
  6. Register both the sale agreement and the construction agreement, and keep stamped copies of every annexure.
  1. மாநில RERA இணையதளத்தில் திட்டப் பதிவைச் சரிபார்த்து, அங்கீகரிக்கப்பட்ட வரைபடத்தையும் அறிவிக்கப்பட்ட காலவரிசையையும் பதிவிறக்குங்கள்.
  2. UDS பரப்பை சதுர அடியில், மொத்த நிலப் பரப்பை, மொத்த வீடுகளின் எண்ணிக்கையைக் கேளுங்கள் — பின்னர் கணக்கை நீங்களே சரிபாருங்கள்.
  3. கூட்டு வளர்ச்சித் திட்டத்தில், உங்கள் UDS-ஐ விற்க பில்டருக்கு அதிகாரம் தரும் வளர்ச்சி ஒப்பந்தத்தையும் அதிகாரப் பத்திரத்தையும் படியுங்கள்.
  4. விவரக்குறிப்புகள் பிராண்ட், தரம், அளவுடன் கையொப்பமிட்ட இணைப்பாக இருக்க வேண்டும் என வலியுறுத்துங்கள் — அடைமொழிகளாக அல்ல.
  5. தவணை அட்டவணையை கட்டுமான மைல்கற்களைப் பின்பற்றும்படி மாற்றுங்கள்; தாமத இழப்பீட்டு விதி, தாமதத் தவணை அபராதத்தைப் பிரதிபலிக்க வேண்டும் எனக் கோருங்கள்.
  6. விற்பனை ஒப்பந்தம் மற்றும் கட்டுமான ஒப்பந்தம் இரண்டையும் பதிவு செய்யுங்கள்; ஒவ்வொரு இணைப்பின் முத்திரையிடப்பட்ட நகலையும் வைத்திருங்கள்.

Frequently asked questionsஅடிக்கடி கேட்கப்படும் கேள்விகள்

The builder says registering the construction agreement is unnecessary. Should I insist?கட்டுமான ஒப்பந்தத்தைப் பதிவு செய்ய வேண்டாம் என்கிறார் பில்டர். வலியுறுத்த வேண்டுமா?

Yes. Registration costs you a little more up front and gives you a document that is far easier to rely on if you have to enforce specifications, timelines or compensation. Reluctance to register the very document that contains the builder's obligations is worth thinking about on its own.

ஆம். பதிவு முன்கூட்டியே சற்று அதிகச் செலவு; ஆனால் விவரக்குறிப்புகள், காலவரிசை அல்லது இழப்பீட்டை அமல்படுத்த வேண்டியிருந்தால், நம்பி முன்வைக்க மிக எளிதான ஆவணத்தைத் தருகிறது. பில்டரின் கடமைகளைக் கொண்ட அதே ஆவணத்தைப் பதிவு செய்ய தயங்குவது, தனியாகவே சிந்திக்கத் தக்கது.

What is UDS and why does the number matter?UDS என்றால் என்ன, அந்த எண் ஏன் முக்கியம்?

UDS is the undivided share of land attached to your flat — your permanent stake in the land, which does not depreciate the way the structure does. It matters for resale value, for your position if the building is ever redeveloped, and for compensation in a land acquisition. A flat with a thin UDS is worth less over the long run than an identical flat with a fair share.

UDS என்பது உங்கள் வீட்டுடன் இணைந்த நிலத்தின் பிரிக்கப்படாத பங்கு — கட்டிடத்தைப் போல தேய்மானம் அடையாத, நிலத்தில் உங்கள் நிரந்தரப் பங்கு. மறுவிற்பனை மதிப்புக்கும், கட்டிடம் மறுவளர்ச்சி செய்யப்பட்டால் உங்கள் நிலைக்கும், நிலம் கையகப்படுத்தப்பட்டால் இழப்பீட்டுக்கும் இது முக்கியம். குறைந்த UDS உள்ள வீடு, நியாயமான பங்குள்ள அதே அளவு வீட்டை விட நீண்ட காலத்தில் குறைந்த மதிப்புடையது.

The builder is a year behind schedule. What can I do?பில்டர் ஓராண்டு தாமதமாகிவிட்டார். நான் என்ன செய்யலாம்?

Start by writing — a dated letter or email recording the delay and asking for a revised schedule creates the record you will need. If the project is RERA-registered, a complaint before the authority seeking interest or compensation is the direct route. Stopping payments unilaterally can put you in breach, so take advice before you do it, and keep paying into the milestones that have genuinely been reached.

எழுத்தில் தொடங்குங்கள் — தாமதத்தைப் பதிவு செய்து, திருத்தப்பட்ட அட்டவணையைக் கோரும் தேதியிட்ட கடிதம் அல்லது மின்னஞ்சல், உங்களுக்குத் தேவைப்படும் ஆவணத்தை உருவாக்கும். திட்டம் RERA-வில் பதிவாகியிருந்தால், வட்டி அல்லது இழப்பீடு கோரி ஆணையத்தில் புகார் அளிப்பதே நேரடி வழி. ஒருதலைப்பட்சமாக பணம் நிறுத்துவது உங்களை ஒப்பந்த மீறலில் நிறுத்தலாம்; அதற்கு முன் ஆலோசனை பெறுங்கள், உண்மையில் எட்டப்பட்ட மைல்கற்களுக்குத் தொடர்ந்து பணம் செலுத்துங்கள்.

Terms explainedசொற்கள் விளக்கம்

UDS (undivided share)UDS (பிரிக்கப்படாத பங்கு)
Your proportionate share in the land under an apartment building, conveyed by a registered sale document.அடுக்குமாடிக் கட்டிடத்தின் கீழுள்ள நிலத்தில் உங்கள் விகிதப் பங்கு; பதிவு செய்யப்பட்ட விற்பனை ஆவணத்தால் மாற்றப்படுவது.
Super built-up areaசூப்பர் பில்ட்-அப் ஏரியா
Carpet area plus walls plus a loaded share of common areas. The basis on which price per square foot is usually quoted.கார்பெட் ஏரியா + சுவர்கள் + பொது இடங்களின் சுமத்தப்பட்ட பங்கு. சதுர அடி விலை பொதுவாக இதன் அடிப்படையிலேயே சொல்லப்படுகிறது.
Joint development agreementகூட்டு வளர்ச்சி ஒப்பந்தம்
The contract between landowner and builder setting out how the built area and land shares are divided between them.கட்டப்பட்ட பரப்பும் நிலப் பங்குகளும் எப்படிப் பிரிக்கப்படும் என்பதை நிர்ணயிக்கும், நில உரிமையாளருக்கும் பில்டருக்கும் இடையிலான ஒப்பந்தம்.
RERARERA
The Real Estate (Regulation and Development) Act framework and the state authority that registers projects and hears buyer complaints.ரியல் எஸ்டேட் (ஒழுங்குமுறை மற்றும் மேம்பாடு) சட்ட அமைப்பு; திட்டங்களைப் பதிவு செய்து வாங்குபவர் புகார்களை விசாரிக்கும் மாநில ஆணையம்.

Referencesசான்றுகள்

Related videosதொடர்புடைய வீடியோக்கள்

Explainerவிளக்கம்7:36
Property Fraud & Scamsசொத்து மோசடி & ஏமாற்று

UDS: how apartment buyers get short-changed on their land shareUDS: அடுக்குமாடி வாங்குபவர்கள் நிலப் பங்கில் எப்படி ஏமாறுகிறார்கள்

The undivided share is your slice of the land under an apartment block. The building depreciates; the land does not — so UDS is the part of the purchase that holds long-tஅடுக்குமாடிக் கட்டிடத்தின் கீழுள்ள நிலத்தில் உங்கள் பங்கே பிரிக்கப்படாத பங்கு (UDS). கட்டிடம் தேய்மானமடையும், நிலம் அடையாது — எனவே நீண்ட காலத்தில் மதிப்பைத் தக்கவைப்பது,

Read explainerவிளக்கம் படிக்க
Explainerவிளக்கம்8:11
Property Documents & Deedsசொத்து ஆவணங்கள் & பத்திரங்கள்

No legal heir certificate? Check the heirs before you buy inherited landவாரிசு சான்றிதழ் இல்லையா? வாரிசுரிமை நிலம் வாங்கும் முன் வாரிசுகளைச் சரிபாருங்கள்

When the owner named in the documents has died, the land no longer belongs to one person — it belongs to all their legal heirs together. A sale signed by only some of theஆவணத்தில் பெயருள்ள உரிமையாளர் இறந்திருந்தால், நிலம் ஒருவருக்குச் சொந்தமானது அல்ல — அவரது அனைத்து சட்டப்பூர்வ வாரிசுகளுக்கும் கூட்டாகச் சொந்தமானது. அவர்களில் சிலர் மட்டும்

Read explainerவிளக்கம் படிக்க
Explainerவிளக்கம்
Property Documents & Deedsசொத்து ஆவணங்கள் & பத்திரங்கள்

Transferring property to blood relatives: the settlement deed explainedரத்த உறவுகளுக்கு சொத்து மாற்றுவது எப்படி? செட்டில்மென்ட் பத்திரம் விளக்கம்

When property moves within a family, the instrument you choose decides the stamp duty you pay, when the transfer takes effect, and whether it can be undone later. A settlகுடும்பத்திற்குள் சொத்து மாறும்போது, நீங்கள் தேர்ந்தெடுக்கும் ஆவணமே செலுத்த வேண்டிய முத்திரைத் தீர்வையையும், மாற்றம் எப்போது நடைமுறைக்கு வருகிறது என்பதையும், பின்னர் அதை

Read explainerவிளக்கம் படிக்க
Explainerவிளக்கம்
Property Fraud & Scamsசொத்து மோசடி & ஏமாற்று

Double registration fraud in Tamil Nadu: the legal steps to reclaim your landதமிழ்நாட்டில் இரட்டைப் பதிவு மோசடி: உங்கள் நிலத்தை மீட்கும் சட்ட வழிமுறைகள்

Double registration is when the same property is sold and registered to more than one buyer, or when a stranger registers a document over land they never owned. The regisஇரட்டைப் பதிவு என்பது, ஒரே சொத்து ஒன்றுக்கு மேற்பட்ட வாங்குபவர்களுக்கு விற்கப்பட்டு பதிவு செய்யப்படுவது, அல்லது ஒருபோதும் சொந்தமில்லாத நிலத்தின் மீது ஒரு அந்நியர் ஆவணம் ப

Read explainerவிளக்கம் படிக்க